Xbloc - Effective ware protection for breakwaters and shores

Shore Protection Bar Beach, Nigeria

The first phase of the project consists of a shore protection of 1 km length, armoured by 1.5 m3 Xblocs®. This coastal erosion control project will solve a long lasting erosion problem that over the past 50 years led to the regression of several hundreds of meters of coastline. The construction has started in January 2006. Bar beach is the first Xbloc® application in Africa.

First use of the Xbloc® special toe unit: Xbase®.This modified Xbloc®, proves to be a stable solution for the toe construction of an armour layer using any concrete single layer armour unit.

It is anticipated that in future the Xbloc® armour will be reused for the shore protection of the Eko Atlantic City project

Project Milestones

February 2006: Start of unit production
April 2006: 1000 XBlocs are cast
May 2006: Start of placement;
placement rates of 12 units per hour are achieved
October 2006: Xbloc seawall put through the test with extreme wave conditions
December 2006: First phase of Bar Beach coastal erosion control project is completed

Project Details

Hs 4.0 m
Length of shore protection 1 km
Size of Xblocs® 1.5 m3

 

 

 

Project pictures

  • Sea wall construction at bar Beach Nigeria
  • Xbloc storage at Bar Beach Nigeria
  • Xbloc Mould at Bar Beach Nigeria
  • The thousandth Xbloc at Bar Beach Nigeria
  • Xbloc storage at Nigeria
  • Xbloc Shore protection at Bar Beach Nigeria
« back to overview